Ip3 Control De Obras [ 95% QUICK ]
| Activity | Hold Point | Acceptance Criteria | |----------|------------|----------------------| | Earthworks | Compaction | ≥95% Proctor density; moisture within ±2% | | Concrete pour | Formwork & rebar | Rebar spacing ±10 mm; cover as per drawing | | Asphalt laydown | Temperature | 140–160°C before compaction | | Welding | Visual & NDT | No cracks; penetration per AWS D1.1 | | Waterproofing | Substrate dryness | Humidity ≤5% (capacitance meter) | Establish frequency (example for roads):